Project Update
Three weeks into the Medical Lake Fire Station remodel and construction is moving quickly and efficiently
We have completed all the major interior demolition, installed underground plumbing, poured new concrete floors and put up CMU walls. Next up this week: steel stud framing, exterior concrete slabs, HVAC and Electrical rough in.
Huge thank you to Steve Moreland our onsite Superintendent and our subcontractors for staying focused on the tasks at hand!